The construction period is 2010-2011, a total investment of 60 million yuan, has entered the stage of being approved. The content of the original project based on the storage system expansion, out of the original part of the reservoir
Cans, the new 1000 m3 storage tank 10, 2000 m3 storage tank 8, 3000 m3 storage tank 12, oil storage capacity of 68,800 cubic meters. The key equipment storage tank, pump, flow transmission, explosion-proof system, anti-
Rot equipment, transport machinery, handling machinery, automated warehousing equipment, track-type stacker, modular shelves, transmission lines, sorting and packaging equipment, air conditioning units, temperature and humidity control systems, equipment monitoring system.